Kilambi News
Saturday, October 17, 2026

Nscale Glomfjord site delayed amid leaks and transformer fire

Technology Saturday, October 17, 2026 · Updated Oct 17, 2026 07:04

Nscale's Glomfjord data center in Norway is reportedly six months behind schedule, with 6.4 megawatts of a planned 30 megawatts operational, after cooling leaks and a transformer fire.

Why it matters: Nscale is preparing an IPO at a reported valuation of up to 35 billion dollars on 103 billion dollars of contracted value; delivery delays at a flagship site go directly to that prospectus risk section.

Data as of Delay reported October 16, 2026 (Bloomberg reporting, via Datacenter Dynamics, with a project source disputing parts of the account in the same article). Single reporting chain, hence grade C. IPO prospectus figures are from the company's September 2026 SEC filing as reported.

Nscale’s data center project in Glomfjord, Norway, is reportedly running six months behind schedule, according to Bloomberg reporting cited by Datacenter Dynamics, after construction delays, local regulation issues, leaks in the cooling system and a transformer fire. Currently 6.4 megawatts of the planned 30 megawatts is operational at the site, and the company has reportedly brought in a floating hotel to house construction workers nearby.

A source familiar with the project disputed parts of that account in the same report, saying the transformer fire occurred in December 2025, temporary generators ran cooling while switchgear was replaced, the leak was resolved within weeks, and while there was an overall delay it was communicated to the customer with no fines or penalties imposed. Datacenter Dynamics said it had contacted Nscale for comment.

The stakes are financial as much as operational. Nscale is preparing an initial public offering at a reported valuation of up to 35 billion dollars, and its September prospectus lists five active data centers offering a combined 55 megawatts with 12 more in development, against 103 billion dollars in total contracted value tied largely to Anthropic and Microsoft contracts. The same prospectus lists construction delays and site accidents among its risk factors, and reports revenue of 140.6 million dollars for the six months to June 2026 against a loss of 1.02 billion dollars.

Sources

  1. Nscale's Glomfjord data center delayed, site suffers leaks in cooling system and a fire · Datacenter Dynamics · 2026-10-16