Kilambi News
Friday, October 30, 2026

Oyu Tolgoi underground pauses, then prepares controlled restart

Mining Friday, October 30, 2026 - Updated Oct 30, 2026 07:08

Rio Tinto paused underground work at Oyu Tolgoi in Mongolia after a seismic event late Thursday triggered a rockfall, and by Friday was preparing a staged restart after inspections found the rockfall localised with no structural impact.

Why it matters: Oyu Tolgoi is Rio Tinto's core copper growth asset, running at an annualised rate of about 450,000 tonnes of copper, so any underground interruption lands on the copper story even when surface work continues.

Data as of Seismic event about 6 p.m. local time Thursday October 29, 2026; pause announced Friday October 30, restart preparation reported later October 30. This is a new development from the October 29 border exports story on this site.

Rio Tinto suspended underground operations at the Oyu Tolgoi copper mine in Mongolia after seismic activity along a rock fault zone at about 6 p.m. local time on Thursday caused ground vibration and a rockfall. The company said three employees were injured and there were no fatalities, and that underground work was paused in line with procedure pending a safety review. Surface milling and open pit mining continued, according to Jefferies analysts cited by Bloomberg.

By Friday the picture had narrowed. Oyu Tolgoi LLC said a preliminary inspection found the rockfall localised and confined, with no structural impact to the cave or its operating infrastructure, and that it was preparing a safe and controlled restart following a systematic staged assessment. Two employees were receiving treatment in Ulaanbaatar for non life threatening injuries, and 13 others were discharged locally after assessment.

Oyu Tolgoi is one of the world’s largest copper and gold deposits, with about 80 percent of its value underground. Rio Tinto owns 66 percent and manages the operation, with the Mongolian government holding 34 percent. The mine has been running at an annualised output rate of about 450,000 tonnes of copper, according to its latest operational update.

Jefferies judged the incident unlikely to have long term impacts on production expectations, which is the right frame if the restart proceeds as described. The pause also arrived in the same week the company flagged delays at the Ganqimaodu border crossing with China that have cut concentrate trucking, covered on this site on October 29, so Oyu Tolgoi’s near term constraint is logistics and safety sequencing rather than geology. Rio Tinto shares fell 3.12 percent in the market tables updated this morning.

Sources

  1. Rio Tinto halts underground operations at major copper mine - Bloomberg via Moneyweb - 2026-10-30
  2. Rio Tinto to restart underground operations at Oyu Tolgoi copper mine, 2nd update - Dow Jones via Morningstar - 2026-10-30
  3. Rio Tinto pauses Oyu Tolgoi underground copper mine after seismic event - Mining.com - 2026-10-29