Kilambi News
Monday, November 2, 2026

Cipher extends Barber Lake lease to 20 years in Q3 update

Infrastructure Monday, November 2, 2026 - Updated Nov 2, 2026 07:45

Cipher Digital's third quarter update on Monday extended its Barber Lake data centre lease to 20 years and about 9.1 billion dollars of contracted revenue, and recorded the company's first high performance computing lease revenue of 5.9 million dollars.

Why it matters: Cipher is one of the bitcoin miners converting power sites into contracted artificial intelligence data centre capacity, and the Barber Lake extension, about 5.2 billion dollars of it incremental, lengthens the contracted book that its 5.4 billion dollars of borrowings rests on.

Data as of Cipher Digital Form 8-K of November 2, 2026, accession 0001819989-26-000047, Exhibit 99.1 read in full via the live browser from EDGAR. Statement figures are in thousands in the filing and are rounded here. Developing item.

Cipher Digital said a lease amendment at its Barber Lake site in Texas adds a second 10 year term with an unnamed leading artificial intelligence lab, taking the lease to 20 years and total contracted revenue at the site to about 9.1 billion dollars, of which about 5.2 billion dollars is incremental. The company recognised its first high performance computing lease revenue in the quarter, 5.9 million dollars from rent commencement at Black Pearl, inside total third quarter revenue of 26.7 million dollars, down from 71.7 million dollars a year earlier as bitcoin mining revenue fell to 20.8 million dollars. GAAP net income was 31.6 million dollars, carried by a 127.2 million dollar gain on the change in fair value of its warrant liability, while adjusted EBITDA was negative 10.0 million dollars against positive 40.8 million dollars a year earlier. Cipher also completed an 850 million dollar offering of zero coupon convertible notes due 2032 to fund further equity investment in Barber Lake, received a conditional 1 gigawatt base load classification for its Colchis site, and put its total development pipeline at about 5.9 gigawatts.

Sources

  1. Cipher Digital Provides Third Quarter 2026 Business Update - Cipher Digital Inc., SEC Form 8-K Exhibit 99.1 - 2026-11-02