UK gigafactory loses second builder in five months

Infrastructure Monday, November 23, 2026 - Updated Nov 23, 2026 07:22

TSL is leaving Tata-owned Agratas's £5.2 billion battery gigafactory in Somerset after failing to agree terms, the second main contractor to walk away from Britain's flagship EV battery project in five months.

Why it matters: The plant is meant to supply Jaguar Land Rover and anchor a domestic battery industry, with £380 million of pledged UK government support; losing a second builder puts its January 2028 production target in doubt.

Data as of The Guardian report of November 23, 2026, read in full via the estate browser. The account rests on unnamed sources close to the project; Agratas says it is on track, and TSL and Jaguar Land Rover declined to comment. Developing item.

Construction specialist TSL, formally Tonroe Group, is leaving Agratas’s £5.2 billion gigafactory at Bridgwater in Somerset after failing to agree terms with the Tata Group battery company, according to The Guardian, with disagreements over the project’s timeline and cost behind the split. TSL is expected to leave the site within two to three months with no replacement main contractor lined up, five months after Agratas dismissed its predecessor, Sir Robert McAlpine, at short notice in June.

The plant, backed by £380 million of pledged UK government support and planned to employ as many as 4,200 people, is now targeting a January 2028 start of production, already pushed back from 2026. Agratas said it is on track to meet customer requirements and that its supplier partners are supporting it well, while Jaguar Land Rover has secured batteries from other suppliers for its first electric models, so those launches are not affected.