Samsung SDI and SK On split Korea's largest storage tender

Infrastructure Thursday, November 26, 2026 - Updated Nov 26, 2026 21:08

South Korea's Ministry of Climate, Energy and Environment awarded its third and largest central ESS tender, 1,194 MW of battery storage, to Samsung SDI with 751 MW and SK On with 443 MW, while LG Energy Solution did not bid.

Why it matters: The central contract market is Korea's main route for grid-scale battery buildout, and the result deepens Samsung SDI's lead in it as scoring shifts from price toward domestic industry contribution and fire safety.

Data as of Yonhap report of November 27, 2026, in Korean, read in full; single source, no second outlet had carried the tender result at check time. Developing item.

South Korea’s Ministry of Climate, Energy and Environment announced the results of the third energy storage tender under its central contract market on November 26, awarding 1,194 MW, about 7.08 GWh of battery capacity and more than the first two tenders combined. Samsung SDI took 751 MW, 62.9 percent of the total, supplying batteries to 9 of the 14 project sites, and SK On took 443 MW, 37.1 percent, across 5 mainland sites. LG Energy Solution, the largest of Korea’s three battery makers by production capacity, did not take part, saying it would focus on delivering volume it has already secured; scoring in the tender has weighted domestic industry contribution and fire safety more heavily since the second round.

Sources

  1. In the largest-ever 3rd ESS government tender, Samsung SDI wins 63%, SK On 37% (in Korean) - Yonhap News Agency - 2026-11-27